BackToProjects
 
ElnaMagnetics
     
“We were pleased that we did not have the stereotypical contractor experience with Meyer Contracting…”
—Joe Ferraro, Elna Magnetics
     

Pre Construction Management: Extensive value engineering and redesign resulted in substantial benefits for the Owner:

  • Value engineering saved $300,000
  • Redesign included foundation, site work, HVAC and electrical fixture package
  • Redesign of mezzanine structural steel provided cost savings on steel and decking
 

Project Description: The project is a pre-engineered metal building with 20,000 square feet of one-story manufacturing and warehouse space, a 1,500 square foot loading dock, 8000 square feet of office space on two levels and an 1,100 square foot break room.

The project was completed with a very aggressive two phase schedule in order to allow manufacturing, shipping and receiving to occupy and being production 6 months after breaking ground and 2+ months prior to offices being completed in November 2009. Sitework was completed by MCC under a separate contract as well.

Project Owner: Elna Magnetics

Architects: Scott Dutton Associates

Project Value: $4.1 million

Completion Date: 2009